- Get written estimate
- Sign contract
- Schedule start date
- 2-4 weeks to start
- Day 1 set posts
- 2-4 business days in between setting posts & hanging gates
- Day 2 install rails, pickets, caps and/or hang gates
Upon getting a written quote from our salesmen and once the contract has been signed we would then schedule a date to start. Depending on how busy we are at that particular time will depend on how long it would take us to start. Most jobs take one day to set all the posts and one day to stretch all the wire and hang the gates.
NOTE: Usually, 2-4 business days between start and finish date for the concrete to cure properly and for time to build your gate(s).